Shipyard Liable For Failing To Obtain Extension Of Refund Guarantee Within A Reasonable Time

A shipyard’s failure to procure a renewal of a refund guarantee (two days before its expiry), was held to be a breach of an implied term of the shipbuilding contract that the shipyard must procure an extension within a reasonable time.

United KingdomTransport

(1) Wuhan Ocean Economic & Technical Cooperation Company Ltd and (2) Nantong Huigang Shipbuilding Co Ltd v. Schiffahrts-Gesellschaft "Hansa Murcia" MBH & Co KG (Hansa Murcia) [2012] EWHC 3104 (Comm)

A shipyard's failure to procure a renewal of a refund guarantee (two days before its expiry), was held to be a breach of an implied term of the shipbuilding contract that the shipyard must procure an extension within a reasonable time. However, this breach was not of itself repudiatory in nature. It was merely breach of an innominate term of the contract which did not deprive the innocent party (the buyers in this case) of "substantially the whole benefit of the contract". As a result, Mr Justice Cooke, on appeal from an arbitration award, held that the buyers were wrong to terminate the shipbuilding contract when they did, two days before the actual expiry date of the refund guarantee.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from