Right To Enforce An "In Rem" Claim Is Not Lost Where The Claim Is Issued After The Court Has Ordered The Sale Of The Vessel

Cargo Interests began proceedings in the U.S. against the Defendant former owner of the M/V SANKO MINERAL for breach of a contract of carriage.

United KingdomTransport

Bank of Tokyo-Mitsuibishi UFJ Ltd v Sanko Mineral (The MV Sanko Mineral) [2014]EWHC 3927 (Admlty)

Cargo Interests began proceedings in the U.S. against the Defendant former owner of the M/V SANKO MINERAL for breach of a contract of carriage. The bill of lading under which the claim was brought incorporated the terms of a charterparty which contained a time bar of 12 months from discharge of cargo.

The Defendant entered reorganisation proceedings in Tokyo, which were recognised by the English court under the Cross-Border Insolvency Regulations 2006. Cargo Interests submitted a claim in the reorganisation proceedings.

An in rem action was issued in the English Admiralty Court by the Claimant bank in respect of a mortgage on the vessel. The Court ordered the sale of the vessel, and that any party with a claim in rem should apply to the court to commence the claim within 60 days. The vessel was sold, and the proceeds paid into court. Within the 60 day period, Cargo