ARTICLE · 12 MARCH 2020

Passage Planning And Unseaworthiness – The Court Of Appeal Decision – CMA CGM LIBRA

The Court of Appeal upheld the decision of the Admiralty Judge in ‘The CMA CGM LIBRA' in that a defective Passage Plan can render a vessel unseaworthy notwithstanding...

United KingdomTransport

The Court of Appeal upheld the decision of the Admiralty Judge in ‘The CMA CGM LIBRA’ in that a defective Passage Plan can render a vessel unseaworthy notwithstanding that the defect stemmed from navigational decisions. Any such error is attributable to the carrier or owner and constitutes a failure by the carrier or owner to exercise ‘due diligence’ before and at the commencement of the voyage to make the vessel seaworthy under the Hague/Hague-Visby Rules. This ruling represents a significant shift of the risk of loss caused by navigational mistakes away from cargo interests and onto owners’ mutuals. 

On 4 March 2020, the Court of Appeal handed down its decision1 on the Owners’ appeal against the earlier decision of the Admiralty Judge, Teare J., which was to the effect that the CMA CGM LIBRA (Vessel) was causatively unseaworthy on account of a defect in her Passage Plan created by the master. Justice Teare had also confirmed that the Owners did not exercise ‘due

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.