Missed Sea Trial Dates Lead To Rescission Of Contracts

A ship buyer succeeded in its claim to rescind two shipbuilding contracts following the shipbuilder's failure to comply with the agreed sea trial dates.

United KingdomTransport
Judith Pastrana
Judith Pastrana

A ship buyer succeeded in its claim to rescind two shipbuilding contracts following the shipbuilder's failure to comply with the agreed sea trial dates. Adyard Abu Dhabi v SD Marine Services (2011)

A shipbuilder was unable to establish successfully before the Commercial Court that there had been a variation of two shipbuilding contracts entitling it to claim breach of contract against the buyer SDMS, a commercial supplier which had commissioned a number of vessels for the UK Government.

Under the shipbuilding contract, the vessels were to be built in compliance with the requirements of the UK Maritime Coastguard Agency (MCA) and the relevant safety codes for special purpose ships (SPS). The shipbuilder argued that new design items imposed by the MCA or SDMS had prevented it from completing the vessels on time for the sea trials. Following the shipyard's failure to comply with the sea trial dates, SDMS purported to exercise its contractual right to rescind the