London Arbitration 1/12, LMLN
3 August 2012
This arbitration concerned owners' claim for loss of time
due to delay in obtaining a berth at the port of discharge.
The background facts
The parties had entered into a voyage charter for the carriage
of steel bars from Poland to Luanda in Angola. En route, the vessel
also picked up a part cargo in Scotland. When the vessel dropped
anchor in Luanda, a notice of readiness (NOR) was tendered. Shortly
thereafter, the Scottish cargo was discharged at a private jetty.
The vessel then had to wait some 11 days before a suitable berth
became available, so that the cargo carried under the present
charter could be discharged. Once at the berth, discharging was
also delayed for a total of 10 hours waiting for trucks for the
cargo. The owners claimed that the time spent waiting for the berth
after completion of discharge of the Scottish cargo, together with
the time lost waiting for the trucks during discharging, was for
the