ARTICLE · 23 NOVEMBER 2016

High Court Financial Loss Not Covered By Shipbuilding Warranty Clause

On 17 November 2016 the High Court ruled that under the warranty clause contained in the shipbuilding contract, the obligation of the Builder after delivery was limited to repair or replace any defects...

United KingdomTransport

On 17 November 2016 the High Court ruled that under the warranty clause contained in the shipbuilding contract, the obligation of the Builder after delivery was limited to repair or replace any defects, and excluded any financial losses caused by the defect. This decision is of significant importance in the shipbuilding industry, since it could define the obligations of Builders after delivery and limit the Builder's exposure to warranty claims more generally. The successful defendant shipyard was represented by Clyde & Co

Star Polaris LLC-v-HHIC-Phil Inc [2016]

The shipbuilding contract in the case was on substantially the SAJ form, with amendments.  The amended Article IX.4 included the wording "except as expressly provided in this paragraph, in no circumstances and on no ground whatsoever shall the builder have any responsibility or liability whatsoever or howsoever arising in respect of or in connection with the vessel or this contract after the delivery of

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from