ARTICLE · 18 JULY 2024

Force Majeure, Exceptions Clauses And Reasonable Endeavours Obligations

The UK Supreme Court ruled that parties can only rely on force majeure clauses if they take reasonable steps to avoid the event's effects but are not required to accept non-contractual performance.

United KingdomTransport

RTI Ltd -v- MUR Shipping BV [2024] UKSC 18

The Supreme Court has unanimously ruled that a party can rely on a force majeure (FM) clause only if it shows that reasonable steps have been taken to avoid the effect of the "force majeure event" (FME) as defined in the clause. 

However, those reasonable steps do not go as far as obliging a party to accept a form of performance that is different to what the parties have agreed in their contract. 

The judgment is important in highlighting the English courts' emphasis on the need for certainty in commercial contracts, particularly in the context of sanctions. 

The background facts

RTI and MUR entered into a contract of affreightment on amended Gencon terms (the COA), which provided for payment of freight to MUR in US dollars. Clause 36 of the COA allowed a party to suspend performance of its contractual obligations on the occurrence of a FME. Pursuant to clause 36.3, an event or state of affairs could be classified

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from