INTRODUCTION
This article considers the measure of damages a Ship-Owner is
entitled to claim, under English Law, from a Charterer who
prematurely re-delivers a vessel in breach of a Time
Charterparty.
The Time Charter is often used to charter a vessel for a period
of time which can range from a few months to several years. This
means that damages can be substantial when the charter is
terminated at an early point. Owners will want to claim what is due
to them under the contract while the Charterer will make every
effort to avoid paying, for example, four years' worth of
charter payments for which they have not had the benefit.
For the sake of clarity parties must be careful to identify
which party has breached the contract, which is not always clear,
as only the 'innocent party' can claim damages. It is also
important to establish whether a party has breached the contract or
whether the contract has been frustrated.