This was an appeal from an LMAA arbitration award, considering the true construction of clause 8(d) of the Inter-Club Agreement 1996 ("ICA"); specifically...

United KingdomTransport

TRANSGRAIN SHIPPING (SINGAPORE) PTE LTD v YANGTZE NAVIGATION (HONG KONG) CO LTD [2016] EWHC 3132

This was an appeal from an LMAA arbitration award, considering the true construction of clause 8(d) of the Inter-Club Agreement 1996 ("ICA"); specifically, whether the meaning of the term "act" in the phrase "act or neglect" should be restricted to a culpable act.

The dispute concerned a trip time charter where the charterers (also the shippers) had, for their own purposes, ordered the ship to wait off the discharge port for over four months before discharging the cargo. During this time part of the cargo was damaged due to overheating, which was found by the Tribunal to have been caused by a combination of the prolonged delay at the discharge port and the inherent nature of the cargo.