Courts Refuse To Help Buyers In Preventing Shipyard Exercising Its Power To Sell Under A Shipbuilding Contract

The Arbitration Act 1996 contains powers for the English courts to make orders where the matter is urgent and the arbitration tribunal has not yet been fully appointed.

United KingdomTransport

Stellar Shipping Company LLP – v - Cosco (Dalian) Shipyard Company Limited [2011] EWHC 1278 (Comm)

The Arbitration Act 1996 contains powers for the English courts to make orders where the matter is urgent and the arbitration tribunal has not yet been fully appointed. In this case, the Court had to decide whether to use such powers to prevent a shipyard exercising its contractual right to sell a newbuilding to a third party, after it had rescinded the shipbuilding contract following an alleged default by the buyer.

Background Facts

The Buyers agreed to buy a 79,000 ton deadweight bulk carrier (the "Vessel") which was to be built by the Shipyard. The price of the Vessel was $49.8m and was payable by way of five instalments.