The Court of Appeal reviews the readiness to load criteria under GAFTA terms and distinguishes it from the requirements of a Notice of Readiness under a charterparty.

In a decision1 certain to please FOB buyers, the Court of Appeal upheld Mr Justice Steel's judgment in Soufflet Negoce v Bunge S.A. (2009). Dismissing Soufflet Negoce's appeal, the Court held that the readiness to load requirement between buyers and sellers under GAFTA terms could not be compared to the Notice of Readiness given by an owner to a charterer.

By a contract dated 19 September 2006, Soufflet Negoce agreed to sell 15,000 tonnes of feed barley, FOB Nikotera, Ukraine. Delivery was stated to be: "Between October 9-22 2006 at buyers' call both dates included. (No extension)." The contract also incorporated the terms of GAFTA contract form number 49. Clause 6 of Gafta 49 governed the period of delivery and stated: