Court Of Appeal Decision In Relation To The Availability Of Damages Once Shipbuilding Contract Terminated

The Court of Appeal has recently handed down its decision in "Stocznia Gydnia SA and Gearbulk Holdings Limited [2009] EWCA Civ. 75".

United KingdomTransport

The Court of Appeal has recently handed down its decision in "Stocznia Gydnia SA and Gearbulk Holdings Limited [2009] EWCA Civ. 75". The Court of Appeal has dealt with the interesting question as to whether, if a Shipbuilding Contract is terminated under the terms of that contract, the buyers' remedy is limited to the recovery of the instalments of the price in accordance with the contract, or whether a claim for damages for repudiation can nevertheless survive. The Court of Appeal held that it could.

1. The Facts

Gearbulk Holdings Limited ("Gearbulk") entered into contracts with Stocznia ("the Yard") for the construction of six vessels for delivery on various dates between 2001 and the end of March 2004. There were separate contracts, but the same in all material respects. The case involved three of those vessels, Hulls 24, 25 and 26.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from