Court Considers Nature Of The Breach And Consequent Measure Of Damages In "Early Redelivery" Case

The vessel was chartered on an amended NYPE form for a minimum of four months and a maximum of five months, plus 15 days in Charterers' option.

United KingdomTransport

Maestro Bulk Ltd v Cosco Bulk Carrier Ltd (The "Great Creation") [2014] EWHC 3978 (Comm)

The vessel was chartered on an amended NYPE form for a minimum of four months and a maximum of five months, plus 15 days in Charterers' option. Hire was at a rate of US$18,500/day gross. Clause 60 of the charterparty dealt with the timing of redelivery notices, and provided:

"On redelivery charterers to tender 20/15/10/7 days approximate and 5/3/2/1 days definite notice."

The earliest date for redelivery was 29 March 2010, and the latest date was 14 May 2010.

On 13 April 2010, Charterers determined that they would not be able to fix another voyage during the currency of the charter and that they would have to redeliver the vessel. On the same day, they served what purported to be a 20 day notice of redelivery. On 14 April they tendered 15/10/7 approximate notices of redelivery, and on 16 April tendered 3/2/1 definite notices. The vessel was redelivered on 19 April. Two