Assessment of Damages Following a Breach of Contract - The "Mamola Challenger"

This case discusses the extent to which a contracting party can claim, as damages for breach of contract, expenditure incurred in preparation of a contract that has been wasted as a result of breach of that contract by the other party. The facts of this claim arose from a breach of a Charterparty by the Charterers.

United KingdomTransport
Ian Woods
Ian Woods

This case discusses the extent to which a contracting party can claim, as damages for breach of contract, expenditure incurred in preparation of a contract that has been wasted as a result of breach of that contract by the other party. The facts of this claim arose from a breach of a Charterparty by the Charterers.

The Owners of the vessel MAMOLA CHALLENGER (the 'Vessel') entered into a 5 year Charterparty with the defendant Charterers who were to sub-charter the Vessel to Shell Nigeria Exploration & Production Company Limited ("SNEPCO"). Under the terms of the Charterparty the Owners had to make modifications to the Vessel prior to delivery which included the installation of a new crane. As a result Owners incurred various expenses in preparation for these modifications including the cost of removing a crane from another Vessel which they intended to install on the MAMOLA CHALLENGER.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from