ARTICLE · 16 OCTOBER 2024

The Importance Of Three Words

Devonshires Solicitors LLP
Devonshires Solicitors LLP
Contributor
Devonshires Solicitors LLP

Devonshires Solicitors LLP

Recognised as industry leaders, with roots that date back to 1841, we have a deep understanding of...

View firm profile
Explore more from Devonshires Solicitors LLP

The Court of Appeal ruled that under the JCT Design and Build Contract, contractors can terminate contracts for repeated defaults, even if earlier defaults were cured. This judgment introduces risks for employers, emphasizing stricter compliance with payment timelines and termination provisions

United KingdomReal Estate and Construction

The Court of Appeal has handed down a judgment on the termination provisions of the 2016 Edition of the JCT Standard Form of Design and Build Contract.

Termination provisions

The amended form of contract allowed the Contractor to issue a notice citing specified defaults (clause 8.9.1). If the specified notice continued for 28 days of the date of that notice, the Contractor may serve a termination notice on, or within, 21 days from the end of the 28-day period (clause 8.9.3). If the contract was not terminated in accordance with clause 8.9.3 "for any reason", the contractor could terminate the contract within 28 days of a repeated specified default.

Relevant facts

In December 2022, the Employer failed to pay a notified sum by the final date for payment. The following day, the Contractor issued a clause 8.9.1 notice. 13 days later, the notified sum was fully paid, ahead of the 28-day period stipulated by clause 8.9.3.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.