It is not often that the FIDIC form of contract comes before the English courts.

United KingdomReal Estate and Construction

It is not often that the FIDIC form of contract comes before the English courts. The primary reason for this is that almost all disputes, if they arise, are settled through arbitration. The case of Doosan Babcock Ltd v Comercializadora de Equipos y Materiales Mabe Limitada1 is one exception.

Why did the court have jurisdiction?

The reason it came before the courts was because Doosan had applied to the Technology and Construction Court ("TCC") asking that the TCC grant relief under section 44(3) of the 1996 Arbitration Act. Section 44 of that Act deals with the court's powers that may be exercisable in support of arbitral proceedings. Under sub-clause 44(3), unless otherwise agreed by the parties, the court has the same power of making orders for the purposes of and in relation to arbitral proceedings as it has for the purposes of and in relation to legal proceedings: