ARTICLE · 08 AUGUST 2024

Sweeper Clauses In The Context Of Safety Concerns

The Upper Tribunal's judgment on 11 July 2024 clarified that a landlord cannot use a 'sweeper clause' to recover costs for remedying structural defects. The case involved the London Borough of Tower Hamlets attempting to charge leaseholders for £8 million in repairs. The Tribunal ruled that the 'sweeper clause' could not cover structural repairs, and such costs require explicit provisions in the lease. This decision emphasizes the need for clear lease terms to recover significant repair costs.

United KingdomReal Estate and Construction

A recent judgment (11 July 2024) of the Upper Tier Tribunal has clarified when a landlord can rely on the 'sweeper clause' in a lease to recover the costs of works needed to the freehold.

Background

London Borough of Tower Hamlets ("the Local Authority") owns the Barleymow Estate in East London which consists of two blocks of flats, owned by long leaseholders (leases of at least 21 years). The blocks were originally constructed using a 'large panel system' ("LPS") whereby mass-produced concrete slabs were bolted together to form the walls and floors of the building. The Local Authority needed to remedy structural defects caused by the LPS. The costs of these works were estimated at £8,066,944.38. The Local Authority sought to recover the costs of these works from the leaseholders.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from