Sharing The Pain: Considerations For Joint Venture Participants

Both contractors and developers often enter into joint ventures to carry out a specific project. It enables parties to bid on larger projects, pool their resources

United KingdomReal Estate and Construction

Both contractors and developers often enter into joint ventures to carry out a specific project. It enables parties to bid on larger projects, pool their resources, including specialised knowledge, and spread risk across the participants. The recent Technology and Construction Court (England and Wales) decision in Doosan Enpure Ltd v Interserve Construction Ltd [2019] EWHC 2497 serves as a reminder to participants in construction joint ventures of the potential pitfalls of intra-JV disputes.

Target cost contracts Under an NEC 3 Option C Contract, a target cost or price is agreed between the parties which includes the contractor's estimate of its "Defined Costs" to carry out the works, plus a fee for its costs, overheads and profit. The contractor is entitled to these costs and its fee, less any "Disallowed Costs", which becomes the final "Price for Work Done to Date". Upon completion, an assessment is made of the "Price for Work Done to Date" and the target cost, as

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from