Breakshore Ltd (Breakshore) employed Red Key Concepts Ltd (Red Key) to construct a six-storey tower block in Kent under a JCT contract. The contractual completion was expected to take place...

United KingdomReal Estate and Construction

The facts

Breakshore Ltd (Breakshore) employed Red Key Concepts Ltd (Red Key) to construct a six-storey tower block in Kent under a JCT contract. The contractual completion was expected to take place May 2021, however, Red Key suspended works in August 2021 on the grounds that the tower block had been built 1.5m taller than the height approved in the planning permission. This pushed back the completion date to October 2021, prompting Breakshore to claim liquidated damages at adjudication.

The adjudicator decided that Red Key should not have paused works without Breakshore's instructions, regardless of the pending revision to the planning permission. Breakshore was awarded £285,523 in liquidated damages for the delayed completion. However, Red Key refused to pay, leading Breakshore to seek enforcement of the adjudicator's decision at the Central London County Court. In turn, Red Key raised a Part 8 claim resisting enforcement of the adjudicator's decision.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from