No Payment Or Pay Less Notice For Final Account? Challenging The Valuation May Still Be Possible

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

However, the scope of the ISG principle has remained unclear, prompting debate as to whether the principle would apply equally to final payments where no valid payment notice or pay less notice has been issued.

United KingdomReal Estate and Construction

Since ISG Construction Ltd v Seevic College [2014] (ISG) it has been established that a party who loses an adjudication for failing to serve a payment notice and/or pay less notice must pay the contractor the notified sum as per the interim application and may not further adjudicate the substantive valuation of that application.

However, the scope of the ISG principle has remained unclear, prompting debate as to whether the principle would apply equally to final payments where no valid payment notice or pay less notice has been issued. The position has been particularly unclear in relation to final payments under the Scheme for Construction Contracts 1998 as amended (the Scheme), which makes no distinction between interim and final payments.