Long lead times for new electricity grid connections are a major impediment to the UK's ability to deliver its commitment to decarbonise the power system by 2035.

United KingdomReal Estate and Construction

Long lead times for new electricity grid connections are a major impediment to the UK's ability to deliver its commitment to decarbonise the power system by 2035. As noted in our previous article on accelerating grid connections, a number of changes are being introduced to speed up the electricity connections process in Great Britain. Longer-term, more fundamental reforms to the connections process are also being consulted upon.

One of the immediate changes is the introduction of a new queue management process for connections to the transmission system, approved by Ofgem last month. This change has been introduced through Connection and Use of System Code (CUSC) modification proposal CMP376 and sees a new Section 16 (Queue Management Process) added to the CUSC.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from