Infrastructure Planning– Changes To Consents For Electricity Storage

From the 2nd December 2020, development consent for electricity storage (except pumped hydro storage) will not need to be sought through the Nationally Significant Infrastructure Project ("NSIP") ...

United KingdomReal Estate and Construction
Alison Ogley
Alison Ogley

From the 2nd December 2020, development consent for electricity storage (except pumped hydro storage) will not need to be sought through the Nationally Significant Infrastructure Project ("NSIP") regime (as currently set out in the Planning Act 2008). Instead, developers will need to seek planning permission from the relevant Local Planning Authority. The changes are being introduced by Infrastructure Planning (Electricity Storage Facilities) Order 2020 SI 2020/1218 ("the Order").

Amendments

  • The Planning Act 2008 ("PA 2008") will be amended to remove electricity storage facilities (except for pumped hydroelectric storage facilities) from the category of generating stations whose construction requires development consent as a NSIP.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from