Had The Developer Used "Reasonable Endeavours"?

The Court of Appeal recently reviewed an agreement where the developer was obliged to use "reasonable endeavours" to resolve matters with third parties prior to the longstop date.

United KingdomReal Estate and Construction

The Court of Appeal recently reviewed an agreement where the developer was obliged to use "reasonable endeavours" to resolve matters with third parties prior to the longstop date. Matters had not been resolved within the 10 year period, so an "Acceptable Planning Permission" had not been obtained and therefore the developer argued that an overage payment of £1.4 million was not triggered. The Court of Appeal considered whether the developer had used "reasonable endeavours" to resolve matters.

The developer argued that in using "reasonable endeavours" it was entitled to have regard to its own profitability and its ability to procure funding.

The Court held that the structure of the interplay of the contracts, including the conditionality that one contract had on another had created the difficulty in procuring funding. This structure was of the developers own making and therefore, the constraints it had created on obtaining funding was self-imposed. The developer