Grove Developments Ltd V S&T (UK) – Will ‘Smash And Grab' Claims Continue?

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

The recent appeal case Grove Developments Ltd v S&T (UK) ("Grove") has triggered a lot of discussion on the impact of ‘smash and grab' adjudications. Here we consider the key points of the case...

United KingdomReal Estate and Construction

The recent appeal case Grove Developments Ltd v S&T (UK) ("Grove") has triggered a lot of discussion on the impact of 'smash and grab' adjudications. Here we consider the key points of the case and its likely effect.

'Smash and Grab' Adjudications

A 'smash and grab' adjudication occurs when either a main contractor or sub-contractor ("payee"), has issued a payment application to an employer or main contractor ("payer"), but the payer has failed to issue a valid payment notice and/or pay less notice in response.

The Housing Grants, Construction and Regeneration Act 1996 ("HGCRA") provides that the sum applied for in the payment application will become due for payment as "the notified sum" if a valid payment or pay less notice is not issued in time. The payer is then obliged to pay this notified sum, whether or not it represents the correct or true value for the works. If the payer does not pay, the payee can raise adjudication proceedings to enforce payment of

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from