As of April 25, 2024, planning enforcement periods were amended, extending the immunity period for most breaches of planning control to 10 years for substantial completions occurring on or after this date.

United KingdomReal Estate and Construction

As of 25 April 2024, planning enforcement periods have been amended by the Planning Act 2008 (Commencement No. 8) and Levelling-Up and Regeneration Act 2023 (Commencement No. 4 and Transitional Provisions) Regulations 2024. Transitional provisions have been included to allow for work where substantial completion took place before 25 April 2024.

These Regulations amend section 171B of the Town and Country Planning Act 1990 so that in most cases, development becomes immune from enforcement if no action is taken:

  • within 10 years of substantial completion for a breach of planning control consisting of operational development where substantial completion took place on or after 25 April 2024.