Building Safety Regulator Reform - A 'Fast Track' Process

Devonshires Solicitors LLP
Devonshires Solicitors LLP
Contributor
Devonshires Solicitors LLP

Devonshires Solicitors LLP

Recognised as industry leaders, with roots that date back to 1841, we have a deep understanding of...

View firm profile
Explore more from Devonshires Solicitors LLP

HRB building control approval applications under the new approval process, known as Gateway 2, have been facing criticism for the significant delays which have a knock on effect to construction projects.

United KingdomReal Estate and Construction

HRB building control approval applications under the new approval process, known as Gateway 2, have been facing criticism for the significant delays which have a knock on effect to construction projects.

Under the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, the time periods for approval of building control approval applications are 12 weeks for new HRBs and 8 weeks for works to existing HRBs. However, in practice, applications are taking in excess of 30 weeks.

This delay is reportedly due to a combination of the lack of capacity in the Building Safety Regulator's ("BSR") outsourced multi-disciplinary teams ("MDT") and the poor quality, or lack of information, in the applications. It has been reported that it can take up to a month just to appoint an MDT which, in of itself, if pushing applications of the prescribed timelines.