The Construction Act permits a party to a construction contract to start an adjudication at any time. But what if a party doesn't want to adjudicate a dispute, and instead commences court proceedings. Can those proceedings be stopped, to allow an adjudication to take place first? This issue arose in DGT v Cubitt.

United KingdomReal Estate and Construction
Rupert Choat
Rupert Choat
Julian Bailey
Julian Bailey
Laura Wood
Laura Wood

The Construction Act permits a party to a construction contract to start an adjudication at any time. But what if a party doesn't want to adjudicate a dispute, and instead commences court proceedings. Can those proceedings be stopped, to allow an adjudication to take place first? This issue arose in DGT v Cubitt.

Cubitt engaged DGT to carry out cladding works. Unusually the subcontract contained a clause providing that ‘any dispute..shall, in the first instance, be submitted to adjudication’, followed by court proceedings if necessary.

DGT sued Cubitt in the TCC for money it claimed was outstanding. Cubitt applied to the court to stop the proceedings, on the basis DGT had breached the agreement to adjudicate. The Court allowed the application and ordered a stay. A key issue was whether there was a binding agreement to adjudicate. The court held that: