ARTICLE · 25 FEBRUARY 2016

A Guide To The UK Construction Market: Understanding Procurement

The traditional route involves the client separately appointing a design team under direct contractual appointments, and maintaining this direct contractual relationship throughout the project. The client appoints the contractor separately under a building contract.

United KingdomReal Estate and Construction

The traditional route involves the client separately appointing a design team under direct contractual appointments, and maintaining this direct contractual relationship throughout the project.  The client appoints the contractor separately under a building contract. 

Design responsibility rests with the design team, and the contractor has a responsibility to build to their design. Although the contractor has no overall design responsibility, he may design discrete specialist items.

Design and build

With design and build, the responsibility for carrying out most, if not all, of the design, and the risk in the design, is passed to the contractor. The contractor may carry out design in house, or may appoint his own design team. Alternatively, the design team appointments originally entered into by the client may be novated to the contractor, allowing for continuity of design.