Triple Point Technology v PTT Public Company Ltd [2019] EWCA Civ 230

The Court of Appeal considered whether a clause conferring daily liquidated damages for delay applied to the particular factual circumstances and, if so, what event brought the liquidated ...

United KingdomLitigation, Mediation & Arbitration

(BAILII entry avilable here)

The Court of Appeal considered whether a clause conferring daily liquidated damages for delay applied to the particular factual circumstances and, if so, what event brought the liquidated damages to an end.

This was a dispute over the purchase of an IT system. Phase 1 of the project was completed 149 days late and further milestones were not completed at all. Ultimately the supplier was held to be in repudiatory breach for abandoning the contract, allowing the customer to terminate.

The contract included liquidated damages for delay which were expressed as accruing:

"…at the rate of 0.1% of undelivered work per day of delay from the due date for delivery up to the date [the customer] accepts such work…".

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from