Navigating Adjudication

Whilst adjudication has been available for a number of decades, legislation passed in 1996 provided statutory legislation as a formal dispute resolution procedure which is available for all construction projects...

United KingdomLitigation, Mediation & Arbitration

Adjudication

Whilst adjudication has been available for a number of decades, legislation passed in 1996 provided statutory legislation as a formal dispute resolution procedure which is available for all construction projects other than contracts for residential homes, unless provided for by the contract itself.

The procedure is fast track. The referring party issues a Notice of Intention to Refer and a nominating body such as the RICS or RIBA appoint an adjudicator. Within seven days of the Notice the referring party then has to issue its claim document (known as a referral) and any supporting information. Subject to an additional 14 days which the adjudicator can seek, the adjudication must be completed within 28 days of issue of the referral.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from