Contractual Dispute Resolution Procedure As A Condition Precedent: Clarity Is Key

Contractual dispute resolution mechanisms intended to avoid or narrow formal disputes through early dialogue are popular, particularly in long-term contracts.

United KingdomLitigation, Mediation & Arbitration

Contractual dispute resolution mechanisms intended to avoid or narrow formal disputes through early dialogue are popular, particularly in long-term contracts.

The case of Kajima Construction Europe (UK) Ltd v Children's Ark Partnership Ltd1 serves as a reminder: a contractual Dispute Resolution Provision ("DRP") can be a condition precedent to commencing proceedings. In a departure from previous case law,2 the High Court in Kajima found a DRP does not actually have to be expressed as a condition precedent to be enforceable as one. However, the DRP does need to be set out as a mandatory obligation that is sufficiently clear and certain – which was not the case in Kajima itself.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from