Ampleforth School was in dispute with its project manager, Turner & Townsend over a building project that was late and over budget.

United KingdomInsurance

Ampleforth Abbey Trust v Turner & Townsend Project Management Ltd [2012] EWHC 2137 (TCC)

Ampleforth School was in dispute with its project manager, Turner & Townsend over a building project that was late and over budget. There were many issues to be determined. One was extent of the clause limiting Turner & Townsend's liability. It stated that liability for any "negligent failure" was to be limited to such liability as was covered by the project manager's professional indemnity insurance and in no event was liability to exceed the lower of fees paid or £1 million. Fees paid amounted to £111,321. In a separate clause, Turner & Townsend was obliged to take out professional indemnity insurance with a limit of indemnity of £10 million. Ampleforth argued that the exclusion clause, being contained in Turner & Townsend's standard terms, was subject to UCTA and unreasonable.