Mitigation Of Loss Coverage: Beware Of Unlimited Coverage

Mitigation of loss coverage is a useful tool for insurers and insureds to limit the impact of design issues in construction projects. In Surespan Structures Ltd. v. Lloyds Underwriters

United KingdomInsurance

Mitigation of loss coverage is a useful tool for insurers and insureds to limit the impact of design issues in construction projects. In Surespan Structures Ltd. v. Lloyds Underwriters [1], the Supreme Court of British Columbia changes the calculus by concluding that no limits apply to a loss mitigation coverage in a project-specific professional liability policy.

Surespan Structures Ltd. ("Surespan") was the design-builder of hospitals and parkades on Vancouver Island (the "Project"). Surespan retained the services of engineering professionals to assist it in the design of the parkades. In late 2016, cracks were discovered in the load-bearing precast elements of the parkades. Surespan undertook remedial work in the order of $9.9 million and sought coverage from the project-specific professional liability insurers for those costs under the loss mitigation provisions of the policy. While several coverage issues were debated by Surespan, the insurers and the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from