SJ, Re [2018] EWCOP 28
Our client, an NHS Hospital Trust, wanted to perform a colostomy
on an adult patient who lacked the capacity to consent. S had an
extensive and deep wound that wouldn't heal and was suffering
sepsis which threatened his life. S's family did not agree with
the treating medical team, and disputed that S lacked capacity, or
that S needed surgery. All of the attempts at exploring concerns
and seeking agreement had been unsuccessful.
After six months as an in-patient, where the 'watchful
waiting' conservative approach had been taken, the Trust had
reduced S's BMI, which significantly reduced the risk of death
associated with the surgery. However, the wound had not healed, the
episodes of sepsis were occurring more frequently and the risk of
developing an antibiotic-resistant infection were high. The
treating medical team wanted S to undergo surgery, to provide the
best chance of recovery; they couldn't agree to stand back and
continue to wait. As