ARTICLE · 06 DECEMBER 2024

UK Coal Mine Planning Consent Quashed

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

The High Court quashed planning permission for the UK's first new deep coal mine in over 30 years, ruling that the government failed to properly assess downstream GHG emissions and climate impact.

United KingdomEnvironment

In December 2022, planning permission was granted by the secretary of state for Levelling Up, Housing and Communities ("SoS") to extract coal from a coal mine in Whitehaven, Cumbria, England. The project would have been the UK's first new deep coal mine in more than 30 years.

Following the grant of permission, Friends of the Earth and South Lakes Action on Climate Change filed court applications seeking statutory review of the UK government's decision (as discussed here). In September 2024, the High Court quashed the permission, ruling that the statutory challenge was successful on four grounds.

The decision comes after the groundbreaking Supreme Court ruling in Finch vs Surrey County Council ("Finch"), which found that the grant of a planning permission for oil production in Surrey was unlawful for failing to assess the "downstream" greenhouse gas ("GHG") emissions that would inevitably arise from the combustion of fuel (as discussed here). Following a similar

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from