Renewables Development: Enforcement Of Planning Permission Conditions

Brodies LLP
Brodies LLP
Contributor
Brodies LLP

Brodies LLP

Brodies LLP is a prominent UK law firm, headquartered in Scotland, that provides expert advice to...

View firm profile
Explore more from Brodies LLP

Experienced developers know that the grant of planning permission is not the end of the process: inevitably there are numerous conditions to fulfil, both pre-commencement and during construction.

United KingdomEnergy and Natural Resources

Experienced developers know that the grant of planning permission is not the end of the process: inevitably there are numerous conditions to fulfil, both pre-commencement and during construction.

Failure to comply with conditions, can lead to the threat of enforcement action by the planning authority.

Private water supplies

Concerns about potential harm to private water supplies led to enforcement and stop notices being served by East Ayrshire Council, requiring all works on the Sneddon Law wind farm development to be stopped, pending production of a water risk assessment. The notices allege breach of a planning condition.

The enforcement notice is currently under appeal, but the legal challenge to the stop notice was unsuccessful.