If the UK Government is to achieve its commitment of delivering
a net zero electricity network by 2035, this will require an
improved and faster grid connections process. National Grid, the
Electricity System Operator (ESO), has announced various
initiatives to address a situation that can occur under the current
process, where viable projects are held back by stalled or slow
moving projects ahead of them in the queue. If you have a project
that has stalled, or if you are behind a stalled or slow moving
project in the queue, these initiatives could be of interest to
you.
Background to the queue
The Transmission Entry Capacity (TEC) register sets out the
‘queue' for all projects which have applied for
connections to the electricity transmission network. Currently,
projects are placed in this queue based on the date they accept
their connection offers and the ESO is not able to optimise the use
of available network capacity by allowing projects with a