If the UK Government is to achieve its commitment of delivering a net zero electricity network by 2035, this will require an improved and faster grid connections process.

United KingdomEnergy and Natural Resources

If the UK Government is to achieve its commitment of delivering a net zero electricity network by 2035, this will require an improved and faster grid connections process. National Grid, the Electricity System Operator (ESO), has announced various initiatives to address a situation that can occur under the current process, where viable projects are held back by stalled or slow moving projects ahead of them in the queue. If you have a project that has stalled, or if you are behind a stalled or slow moving project in the queue, these initiatives could be of interest to you.

Background to the queue

The Transmission Entry Capacity (TEC) register sets out the ‘queue' for all projects which have applied for connections to the electricity transmission network. Currently, projects are placed in this queue based on the date they accept their connection offers and the ESO is not able to optimise the use of available network capacity by allowing projects with a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from