In its spending review the Government announced two changes to
the CRC Energy Efficiency Scheme which fundamentally alter the
nature of the scheme.
Recycling payments
Instead of the scheme being "revenue neutral" and the
net costs of allowances being recycled to participants, the revenue
generated from the sale of allowances will now be retained by the
Government. The Government estimates that this will amount to
£1billion by 2014-2015.
As each allowance will initially cost £12 and an allowance
is needed for each tonne of carbon consumed, the costs of CRC will
increase significantly for each participant. The British
Property Federation are urging the Government to provide more
details as participants are already making provision for this
scheme. In the meantime any landlord participant that had
decided not to deal with CRC in its leases because of the
relatively low costs involved might want to reconsider.