The recent High Court judgment in AstraZeneca (AZ) v IBM (22/11/11), in which the Court was required to interpret the exit provisions in an IT outsourcing contract, serves as a reminder of the importance to both parties of ensuring that the exit terms of the contract receive careful attention at the contract negotiation stage, and that the terms governing the exit arrangements are clear and unambiguous, particularly as these terms will be invoked at a time when the parties’ interests are no long

United KingdomEmployment and HR
Paul O'Hare
Paul O'Hare
Chris Hawkins
Chris Hawkins

The recent High Court judgment in AstraZeneca (AZ) v IBM (22/11/11), in which the Court was required to interpret the exit provisions in an IT outsourcing contract, serves as a reminder of the importance to both parties of ensuring that the exit terms of the contract receive careful attention at the contract negotiation stage, and that the terms governing the exit arrangements are clear and unambiguous, particularly as these terms will be invoked at a time when the parties' interests are no longer aligned, and when the commercial relationship between the parties has potentially broken down.

Background

AZ and IBM entered into an outsourcing services agreement in 2007 for the provision of IT infrastructure services from IBM's data centre facilities in the UK, Sweden, USA and Japan. Some of the services were provided using systems and infrastructure that were also used to provide similar services to other IBM customers.