Following the temporary restrictions on winding-up
petitions brought in under the Corporate Insolvency and Governance
Act 2020 being lifted, as Jatinder Garcha sets out, we are left
with a contracting market still working its way through the ripples
of Brexit, Covid-19, labour and material shortages, price
fluctuations and just about the toughest Professional Indemnity
insurance market we have seen.
With the prospect of insolvency related terminations of building
contracts taking place over the coming months, this article
considers some of the implications of taking over and completing a
half done construction project.
Patience is golden
Seeing your completion date drift further and further away is
frustrating and can trigger knee-jerk reactions. Employers need to
be very careful not to instruct another contractor to undertake
works that are already contracted to the existing contractor under
a live building contract.1