The decision of the Scots Inner House in July last year
dismissing appeals in the City Inn litigation has provoked
considerable debate. The Inner House approved an apportionment
approach to the granting of EOTs under JCT-style contract clauses,
whereas the availability of such an approach is questionable under
English law. A recent TCC decision has now brought the debate into
sharp focus by confirming what is thought to be the English
position.
In 2007, De Beers commissioned a large software development
project aimed at upgrading its diamond handling systems and
supporting the relocation of various processing activities from
London to Botswana. The project was put out to tender and a
contract was awarded to Atos. The project fell behind schedule, due
in part to additional works ordered by De Beers and in part due to
matters for which Atos was responsible (such as unrealistic tender
assumptions).