The Importance Of As-Built Programmes In Construction Disputes

It is trite that many projects in the UAE are completed late. The issues flowing from late completion are: (i) what was the cause; (ii) who was responsible; and (iii) what compensation is due (if any).

United Arab EmiratesReal Estate and Construction
Dean O'Leary
Dean O'Leary

It is trite that many projects in the UAE are completed late.

The issues flowing from late completion are: (i) what was the cause; (ii) who was responsible; and (iii) what compensation is due (if any).

When pursuing delay claims proof will be needed to demonstrate that:

  • the event actually took place;
  • the event is catered for within the contract;
  • the relevant notices have been issued;
  • the event had a delaying effect on the completion date;1 and
  • a loss was suffered as a result of this delay.

The above go to demonstrating what is colloquially known as 'cause and effect'. This article seeks to explain the importance of an as-built programme when trying to resolve delay claims.