Introduction
The main obligation of the contractor in the contract of work is
to create the work and deliver it to the owner. In order to be able
to deliver the work on time, the work for the creation of the work
must be started on time and this work must
continue1.
Article 473 of the Turkish Code of Obligations provides the
owner with an opportunity to apply before the contractor's
obligation to deliver the work becomes due. Pursuant to this
provision, if the contractor delays in starting the work, slows
down the work or it is understood that the contractor will not be
able to complete the work on time, the owner may rescind the
contract. In order to use the right of rescission, the delay must
be caused by a reason that cannot be attributed to the owner.
Pursuant to the aforementioned provision, although it is not
necessary for the contractor to be at fault in order to rescind the
contract, the delay in the work must be in breach of the
contract2.