ARTICLE · 02 APRIL 2019

A Win For Independent Power Producers

Yesterday (26 March 2019), Judge P.A. Meyer handed down judgment in the High Court of South Africa (Gauteng Division, Pretoria) dismissing the application by the Coal Transporters Forum.

South AfricaEnergy and Natural Resources

Yesterday (26 March 2019), Judge P.A. Meyer handed down judgment in the High Court of South Africa (Gauteng Division, Pretoria) dismissing the application by the Coal Transporters Forum. The application was to interdict Eskom from entering into power purchase agreements with three Independent Power Producers (IPPs) in the Small Project Programme and to declare the power purchase agreements already concluded by Eskom in Bid Window 4 of the Renewable Energy Independent Power Producer Procurement Program invalid.

The judgment reflects on the development of the South African government's integrated resource plan which, although recognising South Africa's dependence on coal as its primary source of power generation, seeks ultimately to reduce carbon emissions and foster a balance of generation technologies.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from