In the recent Supreme Court ("the
Court") case of SC.332/2009;
Julius Berger Nigeria Plc. & Anor. v. Toki Rainbow
Community Bank Ltd, Julius Berger, the appellant, by a
local purchase order requested a Contractor to make a supply to it
("the Contract"). The Contractor
approached Toki Rainbow Community Bank Ltd, the respondent, to
grant it a loan to enable it execute the Contract. The
respondent's condition for giving the Contractor the loan was
for the Contractor to domicile all payments under the Contract with
it. The respondent signed a loan agreement and domiciliation
agreement with the Contractor before granting the loan.
Upon failure of the appellant to domicile payments under the
Contract with the respondent, the respondent commenced an action
against the appellant for payments due to the Contractor under the
Contract. Both the trial Court and the Court of Appeal held that
the domiciliation agreement between the Contractor and respondent
amounts to an