ARTICLE · 15 OCTOBER 2019

Is It Time To End Retention Payments?

RDJ LLP
RDJ LLP
Contributor
RDJ LLP

RDJ LLP

RDJ is one of Ireland’s leading corporate law firms. With more than 300 employees and offices in...

View firm profile
Explore more from RDJ LLP

FINOLA MCCARTHY, Partner, Ronan Daly Jermyn, examines alternative means to retention of providing protection for clients, and questions what real value retention brings to projects.

IrelandReal Estate and Construction

Retention is a longstanding feature of construction and engineering projects whereby a percentage of the contract price is withheld by the client as a safeguard against remedying defects. Half is released at project completion, and the other half is released following the expiry of a defects liability period. In preparing contracts, the debate is generally focused on the percentage of retention that is to be applied, and the question of whether or not retention is appropriate is not considered.

Is the time now right to review this practice?

The Issues

The retention of money has a considerable impact on cash flow for contractors and subcontractors, and many have experienced delays in the release of retention monies at the end of a project without justification. Research carried out in the United Kingdom in 2017 found that 71% of contractors surveyed experienced delays in receiving retention monies over a three-year period, with over half of those surveyed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from