Supreme Court Sets New Rules On Delay In Security For Costs Applications

RDJ LLP
RDJ LLP
Contributor
RDJ LLP

RDJ LLP

RDJ is one of Ireland’s leading corporate law firms. With more than 300 employees and offices in...

View firm profile
Explore more from RDJ LLP

In the most significant ruling on security for costs in many years, the Supreme Court has delivered a judgment clarifying the operation of security for costs and providing important guidance for litigants and practitioners.

IrelandLitigation, Mediation & Arbitration

Introduction

In the most significant ruling on security for costs in many years, the Supreme Court has delivered a judgment clarifying the operation of security for costs and providing important guidance for litigants and practitioners.

Where a plaintiff company is unlikely to be able to meet a costs award, a defendant may apply for security for costs under section 52 of the Companies Act 2014. Courts retain a discretion to refuse such an order where "special circumstances" exist, one of which is undue delay on the part of the applicant.

In Sweeney & The Limerick Private Ltd v VHI, the Court has, for the first time, set out a clear, graduated framework for assessing delay as a "special circumstance". The judgment explains when delay begins to run, what level of prejudice must be shown, and when delay alone may justify refusing security. Anyone involved in, or contemplating, a security for costs application should take careful note of these principles.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from