Court Considers Where The Balance Of Justice Lies In Dismissing Claims For Delay

Taking these principles into account, the court felt that the balance of justice lay in favour of allowing the plaintiff to continue her claim, although she should do so with the greatest despatch possible.

IrelandLitigation, Mediation & Arbitration

A recent decision(1) has usefully synthesised the principles applicable to dismissing claims for delay, which in this case had been brought by the seventh defendant. The decision also clarifies that the courts will engage in a case-by-case analysis of where the balance of justice lies, in terms of whether to allow a plaintiff to continue its claim or whether a defendant should not be obliged to defend proceedings which are not progressed with sufficient expedition.

Facts

The plaintiff purchased an apartment, in respect of which the seventh defendant (who had been retained as the structural and civil engineer on the development) had attested to the development's compliance with building regulations. However, the apartment had issues with cracked walls, ongoing water ingress and other continuing problems. The developer – the first defendant in the proceedings – had undertaken some remedial work in the development over the years, but went into liquidation in 2009.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from