Renewables Update, March 2012

In this update, we look at a range of topical issues relevant to the Irish renewable sector including Wind Turbine Planning, Tie-breaks, constraints and curtailment, the Construction Contracts Bill, and REFIT 2 & 3.

IrelandEnergy and Natural Resources

In this update, we look at a range of topical issues relevant to the Irish renewable sector.

Wind Turbine Planning

A recent ruling by An Bord Pleanála (the 'Board') has cast doubt on the ability of developers to substitute larger turbines to those described in applications that have been granted planning permission.

Planning permission had been granted by the Board to erect four Gamesa G58 turbines. Subsequently, the local planning authority agreed in writing that two of those G58 turbines could be substituted for G80 turbines but at a lower hub height on the basis that these changes were immaterial. Having received express written agreement to the alteration/ deviation from the planning authority, the developer secured funding and installed two G80 turbines and one G58 turbine. Several years later, the Board was requested to consider whether the installed G80 turbines were within the scope of the original planning permission. In making its ruling, the Board

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from