"Computatıon Of Loss Of Profıt" By An Arbıtrator In Constructıon Contracts

Disputes arising due to delay in completion of an infrastructure construction contract may lead to a variety of claims, including that of claims towards loss of profit, liquidated damages...

IndiaReal Estate and Construction

Introduction

Disputes arising due to delay in completion of an infrastructure construction contract may lead to a variety of claims, including that of claims towards loss of profit, liquidated damages, damages due to idling of plant, labour and machinery and increase in onsite and offsite over-head expenses. The law with respect to grant of damages, whether liquidated or unliquidated, has been discussed by the courts in a plethora of judgments. However, claims pertaining to loss of profit and profitability have been seldomly discussed.

The Supreme Court, recently in Batliboi Environmental Engineers Limited vs. Hindustan Petroleum Corporation Limited and Another1 (hereinafter referred to as “Batliboi”) was seized with a claim for loss of profit and profitability and considered the decision of the Arbitrator to award 10% of the contract value towards loss of overheads and another 10% towards loss of profits/profitability.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from